View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7799
Project Title: Advance Planning: Computer Room Cooling System Upgrade (State Computer Facility)
Agency: EITS
Division: EITS
Department: Admin
Project Manager: DBN
Description: Advance planning through construction documents for replacement of the existing air conditioning equipment that serves the main server room at the Computer Facility.
Location: Carson City
DI_Location_2: 0
Project Description: The scope of work for this project is to provide advance planning through construction documents for replacement of the existing air conditioning equipment that serves the main server room at the State Computer Facility in Carson City. The planning and design of the new cooling system will include an evaluation of alternative system types and an evaluation of construction phasing (phasing as required to keep the server room in operation during construction).

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Computer Room AC Units (20 ton) (3 ea @ $90,000/ea) 270,000
2 Air Distribution System Modifications (3 ea @ $15,000/ea) 45,000
3 Electrical Modifications 15,000
4 Temperature Control System Modifications 30,000
5 Removal & Disposal of Existing Equipment 10,000
6 Crane/Rigging 5,000
7 Testing, Balancing, & Commissioning 10,000
8 Roof Curbs & Roofing Modifications 15,000
9
10
11
12
13
14
15
16
Total 400,000