View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7712
Project Title: Pavement Maintenance at the Boulder City RR Museum
Agency: RR_Mus
Division: MusHist
Department: T&CultAffr
Project Manager: MJM
Description: Patch, crack seal, slurry seal and restripe the existing AC pavement.
Location: Boulder City
DI_Location_2: 0
Project Description: This project will make minor repairs to failing pavement, and perform maintenance and re-striping of the remainder of the pavement.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Miscellaneous Patching (2,000 sf @ $10/sf) 20,000
2 Crack Seal (34,000 sf @ $.05/sf) 1,700
3 Sealing (34,000 sf @ $.45/sf) 15,300
4 ADA Striping - 2 Additional (7 ea @ $40/ea) 280
5 Parking Striping (52 ea @ $12/ea) 624
6 ADA Signage & Posts (2 ea @ $350/ea) 700
7
8
9
10
11
12
13
14
15
16
Total 38,604