SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7701
Project Title: Replace Packaged HVAC Units (Pinion Hall at WNC Fallon Campus)
Agency: WNC
Division: WNC
Department: NSHE
Project Manager: DBN
Description: Replace existing roof-mounted packaged gas-electric units serving Pinion Hall at the Western Nevada College Fallon Campus.
Location: Fallon
DI_Location_2: 0
Project Description: This scope of work for this project is to replace the rooftop packaged heating and cooling units that serve Pinion Hall at the Western Nevada College Campus in Fallon.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Packaged Rooftop Unit (4 ton) (2 ea @ $7,000/ea) 14,000
2 Packaged Rooftop Unit (5 ton) 8,000
3 Packaged Rooftop Unit (10 ton) (2 ea @ $14,000/ea) 28,000
4 Ductwork Modifications 8,000
5 Roof Curb Modifications 15,000
6 Gas & Condensate Piping Modifications 2,000
7 Electrical Modifications 9,000
8 Temperature Control System Modifications 20,000
9 Testing, Balancing, & Commissioning 8,000
10 Crane/Rigging 12,000
11 Removal & Disposal of Existing Equipment 6,000
12
13
14
15
16
Total 130,000