View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7700
Project Title: Advance Planning: Replace Multi-Zone HVAC Unit (Sage Hall at WNC Fallon Campus)
Agency: WNC
Division: WNC
Department: NSHE
Project Manager: DBN
Description: Advance planning through construction documents for replacement of the existing roof-mounted multi-zone unit that serves Sage Hall at the WNC Fallon campus.
Location: Fallon
DI_Location_2: 0
Project Description: The scope of work for this project is to provide advance planning through construction documents for replacement of the existing rooftop multi-zone heating and cooling unit that serves Sage Hall at the Western Nevada College campus in Fallon. This project will be best served by funding a planning project due to the fact that the campus facilities staff would prefer replacing the multi-zone unit with multiple smaller single zone packaged gas-electric units. This approach will require a structural evaluation as well as an assessment of the appropriate thermal zoning.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Rooftop Multi-Zone Unit (9,000 cfm - 7 Zones) 90,000
2 Roof Curb & Duct Modifications 10,000
3 Gas & Condensate Piping Modifications 4,000
4 Electrical Modifications 4,000
5 Temperature Control System Modifications 10,000
6 Testing, Balancing, & Commissioning 9,000
7 Crane/Rigging 7,000
8 Removal & Disposal of Existing Equipment 5,000
9
10
11
12
13
14
15
16
Total 139,000