View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7693
Project Title: Generator Replacement (Reno Purchasing Warehouse)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: CAD
Description: This project upgrades the 140 kW generator with a 250 kW generator.
Location: Reno
DI_Location_2: 0
Project Description: The proposed single generator will be 250 kW and will handle the whole building load.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace 250 kW Generator 140,000
2 Transfer Switch 40,000
3 Installation (Demo, Bollards, Pad, Wiring & Repairs) 75,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 255,000