View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7690
Project Title: Site Drainage Improvements (Frankie Sue Building)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: BJW
Description: Construct PCC sidewalk and trench drain on the west side of the Frankie Sue Building to improve site drainage.
Location: Carson City
DI_Location_2: 0
Project Description: This project will design and construct drainage improvements to direct storm flows away from the building foundation on the west side of the Frankie Sue Building. The project scope involves removal and replacement of PCC sidewalk, installation of a trench drain, and connection of two building drains into storm drain piping.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remove & Replace PCC Sidewalk (1,000 sf @ $30/sf) 30,000
2 Trench Drain (100 lf @ $160/lf) 16,000
3 Building Drain Connection (2 ea @ $12,500/ea) 25,000
4.
5.
6.
7
8
9
10
11
12
13
14
15
16
Total 71,000