Description: Remove and replace the exterior concrete ramps and stairs for safety & ADA compliance
Location: Stewart
DI_Location_2: 0
Project Description: This Project will remove and replace the existing exterior concrete ramps and stairs to Building 89 at the Stewart Complex. The above work will comply with the Americans With Disabilities Act.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remove / Replace ADA Ramp West Entrance 50,000
2 Remove / Replace Stairs West Entrance 5,000
3 Remove / Replace Stairs / Landing South Entrance 6,000
4 Remove / Replace Ramp / Stairs North Entrance 25,000
5 AC Paving Patching (100 sf @ $10/sf) 1,000
6 Landscaping (300 sf @ $4.5/sf) 1,350
7 Handrails (300 lf @ $40/lf) 12,000
8.
9.
10.
11.
12
13
14
15
16
Total 100,350