View Recomended 2019 CIP Data
SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals.
Please review the data, if any adjustments need to be made please contact SPWD.
Application ID:
7679
Project Title:
ADA Site Upgrades to B&G Facilities
Agency:
B&G
Division:
SPWD
Department:
Admin
Project Manager:
MCR
Description:
Replace existing concrete sidewalks with new sidewalks and ramp to bring site into ADA compliance
Location:
Carson City
DI_Location_2:
0
Project Description:
This project will remove and replace concrete sidewalks and a concrete ramp around buildings' 1, 2, 90 and 107 at the Stewart Campus. The work will include removal and replacement of damaged and non ADA compliant concrete along ADA routes of travel betwee
SPWD Construction Cost Estimate from June 2016
Line Item |
Cost |
1 ADA Concrete Ramp |
50,000 |
2 Replace 4" PCC Sidewalks (5,000 sf @ $12/sf) |
60,000 |
3 Handrails (150 lf @ $40/lf) |
6,000 |
4 Landscaping (1,000 sf @ $5/sf) |
5,000 |
5. |
|
6. |
|
7. |
|
8. |
|
9 |
|
10 |
|
11 |
|
12 |
|
13 |
|
14 |
|
15 |
|
16 |
|
Total |
121,000 |
|