View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7675h
Project Title: Replace Door Hardware in B&G Managed Buildings
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: RMO
Description: Replace all door hardware, both interior and exterior doors, in DMV/DPS - Carson City .
Location: Carson City
DI_Location_2: 0
Project Description: The scope of this project is replace the door hardware in the Carson City DMV/NHP building. This project will standardize the door hardware ensuring that the same manufacturer is used throughout all of the buildings. B&G's goal is to make the door hardware types, color, finish, and style consistent throughout the various State buildings in Carson City. This project is a first step in achieving that goal.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 DMV/DPS -Carson City (140 ea @ $1,200/ea) 168,000
2
3
4
5.
6
7
8
9
10
11
12
13
14
15
16
Total 168,000