Application ID: 7675
Project Title: Replace Door Hardware in B&G Managed Buildings
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: RMO
Description: Replace all door hardware, both interior and exterior doors, in three buildings. Building No. 6-Stewart, EICON Building, and Frankie Sue Del Papa Building -Carson City
Location: Carson City
DI_Location_2: 0
Project Description: The scope of this project is replace the door hardware in three buildings. This project will standardize the door hardware ensuring that the same manufacturer is used throughout all of the buildings. B&G's goal is to make the door hardware types, color, finish, and style consistent throughout the various State buildings in Carson City. This project is a first step in achieving that goal.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Building No 6-Stewart (60 ea @ $1,200/ea) 72,000
2.EICON Building (109 ea @ $1,200/ea) 130,800
3 Frankie Sue Del Papa Building (48 ea @ $1,200/ea) 57,600
4
5.
6
7
8
9
10
11
12
13
14
15
16
Total 260,400