View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7673
Project Title: Replace Plumbing Fixtures (Various Buildings at Stewart Facility)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: DBN
Description: Replace urinals and faucets in various buildings at the Stewart Facility with new water-conserving fixtures.
Location: Stewart
DI_Location_2: 0
Project Description: The scope of work for this project is to replace the existing urinals and the existing lavatory faucets in various buildings located at the Stewart Facility in Carson City. The new fixtures will result in more than a 50% reduction in water usage by the associated fixtures. The buildings include Building 3 (Museum), Building 6 (Administration POST), Building 12 (Dormitory), Building 13 (Dormitory), Building 18 (NDOC Offices), and Building 89 (NDOC Administration).

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Urinals with Flush Valves (10 ea @ $2,600/ea) 26,000
2 Sensor-Operated Faucets (55 ea @ $800/ea) 44,000
3 Demolition & Disposal of Existing Fixtures 5,000
4 Shut-Off Valves & Piping Connections 6,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 81,000