View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7667
Project Title: Infrastructure Improvements (UNLV Beam Hall)
Agency: UNLV
Division: UNLV
Department: NSHE
Project Manager: LAR
Description: Replacement of HVAC equipment serving several floors, replacement of water piping, door hardware, flooring, and access control improvements.
Location: Las Vegas
DI_Location_2: 0
Project Description: The infrastructure improvements for the UNLV Frank and Estella Beam Hall include the replacement of HVAC units in three floors of the building, replacement of water piping for the mechanical units, replacement of door hardware, additional card readers, replacement of flooring, painting of offices/classrooms, and an epoxy treatment.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Mechanical Renovation 2,516,481
2 Balancing, Commissioning & Water Treatment 125,000
3 Door Hardware (387 ea @ $400/ea) 154,800
4 Card Readers (15 ea @ $4,000/ea) 60,000
5 Flooring (50,000 sf @ $11.64/sf) 582,000
6 Paint Offices & Classrooms (160,000 sf @ $1.66/sf) 265,600
7 Remove Existing Tile Floor & Prep Floor (3,000 sf @ $4/sf) 12,000
8 Epoxy Treatment (7,000 ea @ $20/ea) 140,000
9 Non-Slip Treatment to Existing Epoxy (13,000 ea @ $10/ea) 130,000
10
11
12
13
14
15
16
Total 3,985,881