Application ID: 7665
Project Title: Building Upgrades (UNLV Carlson Education Building)
Agency: UNLV
Division: UNLV
Department: NSHE
Project Manager: LAR
Description: Install fire sprinklers, upgrade fire alarm system, upgrade data/phone/telecom, remodel restrooms, and perform selective hazardous material abatement.
Location: Las Vegas
DI_Location_2: 0
Project Description: This request is to install a fire sprinkler system in the existing and occupied Carlson Education Building. Abatement, demolition and removal of asbestos-containing ceilings and flooring related to this sprinkler installation, as well as improvement of the existing fire alarm system, restrooms and the data cabling system will be conducted. Minimal data and phone cable will be replaced. This cabling will be installed in new conduit to meet current UNLV Office of Information Technology standards for data ports and Voice over Internet Protocol capability. Due to the fully occupied building and the sequencing requirements for minimal disruption of the students and faculty, the Construction Manager At Risk (CMAR) delivery method will be utilized for this project.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Ceiling Demolition (50,000 sf @ $1.3/sf) 65,000
2 Ceiling Replacement (50,000 sf @ $7/sf) 350,000
3 Selective Flooring Replacement (5,000 sf @ $11.64/sf) 58,200
4 Fire Alarm System Upgrades (100,000 sf @ $6.5/sf) 650,000
5 Raceways/Conduits (100,000 sf @ $7/sf) 700,000
6 Fire Sprinkler System (100,000 sf @ $9/sf) 900,000
7 Fire Main Services (70 lf @ $400/lf) 28,000
8 Fire Riser Room & Fire Pump Room (350 sf @ $250/sf) 87,500
9 Miscellaneous Concrete Coring (70,000 ea @ $1/ea) 70,000
10 Six Restroom Remodels (6 ea @ $45,000/ea) 270,000
11 Shafts/Texture/Painting/Patching (50,000 ea @ $1/ea) 50,000
12 Remove Existing Data Line to Building 5,000
13 Replace Fiber Optic Line (4,900 lf @ $50.22/lf) 246,078
14 Telecom/Phone/Data Equipment (697,200 ea @ $1/sf) 697,200
15 Scoping of Sewer Lines 6,000
16 Fire Pump/Equipment/Electrical 80,000
Total 4,182,978