Description: Planning through Construction of a 130,000 sf office building on the Sahara complex. This project includes the demolition of the Bradley Building.
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of this project is to provide advanced planning through construction for the development of one building for Buildings and Grounds to rent to state agencies. This building is to be located on the Sahara Complex near the new DMV and DETR buildings. The 130,000 sf building will provide office space for certain State Agencies currently in leased space. The furnishings and equipment has been deferred to the 2019 CIP.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Building (130,000 ea @ $290/ea) 37,700,000
2 Bradley Building Demolition 500,000
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 38,200,000