Application ID: 7644
Project Title: New Maintenance Shop (NNVMC)
Agency: VetSvc
Division: VetSvc
Department: VetSvc
Project Manager: RLC
Description: The demolition of two aged maintenance structures and construct a new 2,600 sf consolidated maintenance facility
Location: Fernley
DI_Location_2: 0
Project Description: This project includes the demolition of two aged maintenance structures and the construction of a new 2,600 sf consolidated maintenance facility. The current structures show signs of failure due to age and exposure. The new maintenance structure will accommodate a welding shop, and taller roll up doors for larger equipment in need of maintenance.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Structures (2 ea @ $15,000/ea) 30,000
2 Site Concrete (2,000 sf @ $10.5/sf) 21,000
3 Pre-Engineered Metal Building (2,600 sf @ $235/sf) 611,000
4 Temporary Storage 20,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 682,000