View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7640
Project Title: Library Renovation/Seismic Retrofit and Central Plant Structure (CSN)
Agency: CSN
Division: CSN
Department: NSHE
Project Manager: LAR
Description: Renovation and seismic upgrade for the Cheyenne campus library; and the Cheyenne Campus north central plant structure.
Location: N. Las Vegas
DI_Location_2: 0
Project Description: The proposed scope of work is for the design and construction of the north central plant building and the renovation/seismic retrofit upgrade for the library at the Cheyenne Campus. For the central plant building, CSN has completed the schematic phase of the construction documents to expand the central plant and the information will be used to design the proposed building. The building will be designed and constructed to allow for the placement of the future equipment in the building. The expansion of the central plant itself will take place in a future phase(s) as funding is made available.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Library Seismic Retrofit 276,461
2 Library Floor Finish (14,388 sf @ $7/sf) 100,716
3 Library Prep & Paint (10,130 sf @ $1.66/sf) 16,816
4 Building for Central Plant (2,600 sf @ $400/sf) 1,040,000
5 Site Development (9,431 sf @ $12/sf) 113,172
6 Central Plant Screen Wall (5,259 sf @ $19/sf) 99,921
7
8.
9.
10
11
12
13
14
15
16
Total 1,647,086