Application ID: 7633
Project Title: Packaged Rooftop Unit Replacement and Lighting Upgrade (Plumb Lane Armory)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: TJD
Description: Replace existing rooftop units, ductwork, and controls. The site exterior lighting and lighting inside the Gym will also be replaced.
Location: Reno
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of the existing rooftop units serving the Gym Building. The scope also includes a complete exterior lighting upgrade (including the flag pole) for all buildings on site as well as an interior lighting upgrade for the Gym Building. New lights will be high efficiency LED type fixtures/lamps. The project also includes replacing the existing rooftop units, ductwork, lighting fixtures, and related controls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment & Ductwork 8,000
2 Packaged Rooftop Unit (3 tons) 4,000
3 Packaged Rooftop Unit (10 tons) 14,500
4 Air Distribution & Ductwork Modifications 7,000
5 Temperature Control System Modifications 25,000
6 Testing, Balancing, & Commissioning 15,000
7 Crane/Rigging 5,000
8 Electrical Modifications 6,000
9 Roof Structure Reinforcement & Fall Protection 7,500
10 Lighting, Conduit, & Wiring 80,000
11 Lighting Controls 10,000
12
13
14
15
16
Total 182,000