Application ID: 7631
Project Title: Storage and Carport Facility (Ely Field Office)
Agency: Wildlife
Division: Wildlife
Department: Wildlife
Project Manager: CSB
Description: Design and construction of a 2,400 sf Office Storage and a 2,000 sf Carport Building
Location: Ely
DI_Location_2: 0
Project Description: The scope of this project is to design and construct a 2,400 sf office storage building and new 2,000 sf covered carport facility at the Nevada Department of Wildlife Ely field office. Once completed, it will provide much needed office storage space and shelter for the office vehicles.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Site Earthwork (1,000 cy @ $25/cy) 25,000
2 Concrete Site Work (4,400 sf @ $15/sf) 66,000
3 Pre-Fabricated Metal Building (2,400 sf @ $90/sf) 216,000
4 Carport Structure (2,000 sf @ $55/sf) 110,000
5 Landscape (3,000 sf @ $4/sf) 12,000
6
7
8
9
10
11
12
13
14
15
16
Total 429,000