Application ID: 7620
Project Title: Pavement Maintenance and Miscellaneous Repairs
Agency: VetSvc
Division: VetSvc
Department: VetSvc
Project Manager: MJM
Description: Patch pavement, replace curbing and re-seal the asphalt in the older sections of the cemetery.
Location: Boulder City
DI_Location_2: 0
Project Description: This project will make miscellaneous repairs to portions of the AC pavement, as well as, some of the PCC curbing, walkways and valley gutters. In addition, it will crack seal, slurry seal and re-stripe the older parts of the AC paving.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Miscellaneous Patching (2,000 sf @ $10/sf) 20,000
2 Curbing (200 lf @ $30/lf) 6,000
3 Sidewalk (100 sf @ $12/sf) 1,200
4 Replace Valley Gutter (30 lf @ $30/lf) 900
5 Crack Seal (85,000 sf @ $.05/sf) 4,250
6 Type 2 Slurry (85,000 sf @ $.4/sf) 34,000
7 Miscellaneous Striping 8,000
8
9
10
11
12
13
14
15
16
Total 74,350