View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7619
Project Title: Chapel Remodel (Southern Nevada Veteran's Memorial Cemetery)
Agency: VetCem
Division: VetCem
Department: VetSvc
Project Manager: LAR
Description: Install protection bollards and replace door hardware and windows.
Location: Boulder City
DI_Location_2: 0
Project Description: The scope of the project includes the installation of protection bollards, the replacement of malfunctioning door hardware and damaged window pane systems.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Hardware (12 ea @ $1,100/ea) 13,200
2 Protection Bollards (4 ea @ $1,500/ea) 6,000
3 Remove Windows 3,500
4 Double Pane Temp Glass Replacement (19 sf @ $63/sf) 1,197
5 Double Pane Glass Replacement (133 ea @ $53/ea) 7,049
6 Miscellaneous Architectural 5,000
7
8
9
10
11
12
13
14
15
16
Total 35,946