Application ID: 7617
Project Title: Remodel Men's restroom (Henderson Armory)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: CSB
Description: Remodel existing Men's restroom at Henderson Armory
Location: Henderson
DI_Location_2: 0
Project Description: The scope of this project is Remodel of existing men's restroom. Once completed, it will provide much needed and upgraded restroom facilities for future soldiers.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Selective Demolition 45,000
2 Mirrors (5 ea @ $500/ea) 2,500
3 Framing, Dry Wall Ceilings & Wall Repair (2,000 sf @ $6/sf) 12,000
4 Ceramic Tile/Walls - Restroom (2,000 sf @ $15/sf) 30,000
5 Epoxy Flooring (1,000 sf @ $30/sf) 30,000
6 Cove Base (200 lf @ $6.75/lf) 1,350
7 Painting Drywall Ceilings & Walls (2,000 sf @ $2/sf) 4,000
8 Toilet Partitions 16,000
9 Toilet Accessories 5,000
10 Toilets (4 ea @ $1,500/ea) 6,000
11 Urinals (4 ea @ $1,500/ea) 6,000
12 Shower Heads, Valves, Rough Carpentry & Sealing 25,000
13
14
15
16
Total 182,850