Application ID: 7611
Project Title: Replace Domestic Water Heaters (Carlin Readiness Center)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: TJD
Description: Replace the existing domestic hot water heaters in 8 buildings at the Carlin Readiness Center.
Location: Carlin
DI_Location_2: 0
Project Description: The scop of work for this project is to replace the existing gas-fired domestic hot water heaters in eight buildings at the Carlin Readiness Center. The project will include replacing existing water heaters, piping, pumps, and related controls. Some of the water heating systems do not include a hot water return piping circuit. This will be added to those water heating systems to conserve water use and provide instant hot water to the low flow plumbing fixtures when used. The buildings proposed for water heater replacement are the Fire Station Building, Turnout Building, Buildings and Grounds Building, Classroom Building, Staff Residence, Administration Building, and the Dining Facility.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment & Piping 15,000
2 Electric Water Heater (50 gallon) (5 ea @ $1,200/ea) 6,000
3 Gas-Fired Water Heater (200 mbh) (2 ea @ $10,000/ea) 20,000
4 Gas-Fired Water Heater (400 mbh) (5 ea @ $15,000/ea) 75,000
5 Flue & Combustion Air Modifications 98,000
6 Tempering Stations with Circulation Pumps (8 ea @ $11,500/ea) 92,000
7 Domestic Water Piping & Accessories 22,000
8 Gas Piping Modifications 6,000
9 Temperature Control System Modifications 25,000
10 Testing, Balancing, & Commissioning 20,000
11 Electrical Modifications 15,000
12
13
14
15
16
Total 394,000