View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7608
Project Title: HVAC Systems Renovation (Carlin Readiness Center)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: TJD
Description: Replace existing water source heat pumps, package rooftop units, piping, ductwork, and related controls.
Location: Carlin
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of heat pumps and rooftop units serving various buildings. Additionally, an access platform addition is proposed in the Classroom Building for proper heat pump access. The mechanical portion of the project includes replacing the existing water source heat pumps, package rooftop units, piping, ductwork, and related controls. The architectural portion of the project includes an access platform as well as some ceiling removal/replacement to facilitate heat pump access and future maintenance.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment & Piping 60,000
2 Water Source Heat Pump (5 tons) (14 ea @ $14,000/ea) 196,000
3 Water Source Heat Pump (8 tons) (10 ea @ $18,000/ea) 180,000
4 Water Source Heat Pump (10 tons) (3 ea @ $22,000/ea) 66,000
5 Packaged Rooftop Unit (2 tons) (2 ea @ $5,500/ea) 11,000
6 Packaged Rooftop Unit (4 tons) 8,500
7 Packaged Rooftop Unit (6 tons) 10,000
8 Packaged Rooftop Unit (12 tons) (2 ea @ $16,000/ea) 32,000
9 Air Distribution & Ductwork Modifications 25,000
10 Condenser Water Piping & Accessories 60,000
11 Temperature Control System Modifications 160,000
12 Testing, Balancing, & Commissioning 25,000
13 Crane/Rigging 10,000
14 Electrical Modifications 65,000
15 Building Modifications 60,000
16
Total 968,500