View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7607
Project Title: Office Upgrades and Addition (Ely Field Office)
Agency: Wildlife
Division: Wildlife
Department: Wildlife
Project Manager: CSB
Description: Design and construction of 1,200 sf office & lab addition, provide existing office building upgrades and parking
Location: Ely
DI_Location_2: 0
Project Description: The scope of this project is to design and construct a 1,200 square foot office/lab addition to the existing building at the Nevada Department of Wildlife Ely field office. The office/lab addition would include a necropsy biological laboratory and 4 staff offices; replace the failing vinyl siding which is no longer available on the existing building with an acrylic stucco to match the new addition; and provide paved access and the parking for agency equipment. This project also includes necessary ADA, fire alarm and sprinkler upgrades to the existing office building.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Clear & Grub 3,000
2 Site Earthwork & Utilities 65,000
3 Concrete Site Work (2,000 sf @ $15/sf) 30,000
4 Office & Lab Addition (1,200 sf @ $300/sf) 360,000
5 Replace Existing Siding withStucco (2,200 sf @ $25/sf) 55,000
6 Tie-in / Re-Roof of Existing Office Building 20,000
7 Gate Modifications 10,000
8 Site Paving, Striping & Signs (12,000 sf @ $10/sf) 120,000
9 (E)-Office ADA, Fire Sprinklers & Alarms (1,720 sf @ $30/sf) 51,600
10
11
12
13
14
15
16
Total 714,600