Application ID: 7606
Project Title: Operations & Maintenance Facility (Mason Valley WMA)
Agency: CNR
Division: CNR
Department: CNR
Project Manager: RMO
Description: Construction Documents thru construction for an operations, maintenance, and equipment storage facility.
Location: Yerington
DI_Location_2: 0
Project Description: The scope of this project is to relocate staff and equipment maintenance and storage facilities from the current Wildlife Management Area (WMA) to the Fish Hatchery. This move will require the design and construction of an office addition to the existing Fish Hatchery Office building to accommodate four additional staff members being transferred (WMA). The project also includes a vehicle and heavy equipment repair garage and a six bay open covered vehicle storage canopy with an exterior wash area. The Department of Wildlife will donate $125,000 to the project.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Office Addition (650 sf @ $320/sf) 208,000
2 Office Remodel (540 sf @ $150/sf) 81,000
3 Heavy Equipment Repair Garage (2,400 sf @ $350/sf) 840,000
4 Covered Equipment Parking (4,800 sf @ $120/sf) 576,000
5 Site Development (1.5 acres @ $10/sf) 653,400
6
7
8
9
10
11
12
13
14
15
16
Total 2,358,400