View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7603
Project Title: Roofing Replacement (Wildlife Rearing Station Building)
Agency: Wildlife
Division: #N/A
Department: #N/A
Project Manager: MHF
Description: This project would provide for a single ply roofing system
Location: Yerington
DI_Location_2: 0
Project Description: This project would provide for a single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition (8,000 ea @ $1/ea) 8,000
2 Roofing - Membrane (8,000 ea @ $10.5/ea) 84,000
3 Gutter - Raceway (1,000 ea @ $20/ea) 20,000
4 Misc Components (8,000 ea @ $1/ea) 8,000
5 Dens Deck (8,000 ea @ $1/ea) 8,000
6 Lift for Gutter 500
7 Down Spouts (20 ea @ $100/ea) 2,000
8 Walk Pad (100 ea @ $5/ea) 500
9
10
11
12
13
14
15
16
Total 131,000