View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7602
Project Title: Preventative Pavement Maintenance (Las Vegas Readiness Center)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: CSB
Description: Crack seal, slurry & re-stripe the asphalt pavement at Las Vegas Readiness Center
Location: Las Vegas
DI_Location_2: 0
Project Description: This project will provide cleaning, crack seal, slurry seal and re-striping of the asphalt pavement in the existing Las Vegas Readiness Center.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Clean & Crack Seal (200,000 sf @ $.13/sf) 25,000
2 Cleaning & Type '2' Slurry Seal (200,000 sf @ $.45/sf) 90,000
3 Parking Striping (320 ea @ $12/ea) 3,840
4 ADA Striping (10 ea @ $35/ea) 350
5
6
7
8
9
10
11
12
13
14
15
16
Total 119,190