View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7601
Project Title: Installation of Culvert
Agency: Wildlife
Division: #N/A
Department: #N/A
Project Manager: MHF
Description: Installation of drainage system
Location: Yerington
DI_Location_2: 0
Project Description: This project would provide for a single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 AC Saw Cutting (120 lf @ $10/lf) 1,200
2 AC Pavement Removal (225 sf @ $10/sf) 2,250
3 Remove & Stockpile Pip Rap (21,600 sf @ $.25/sf) 5,400
4 Slope Grade (21,600 sf @ $.3/sf) 6,480
5 3' Wide Valley Gutter (1,080 lf @ $45/lf) 48,600
6 Drainage Inlet (4 ea @ $1,500/ea) 6,000
7 Pvc Pipe (45 lf @ $50/lf) 2,250
8 Storm Drain Connections (4 ea @ $1,000/ea) 4,000
9 AC Patching (225 sf @ $10/sf) 2,250
10 Replace Riprap (21,600 sf @ $.25/sf) 5,400
11
12
13
14
15
16
Total 83,830