View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7600
Project Title: HVAC Systems Renovation (Office of the Adjutant General)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: TJD
Description: Replace existing outdoor air handler, rooftop units, and add new system to dining area and auditorium office. Includes ductwork, piping, and controls.
Location: Carson City
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of five (5) existing rooftop air handlers, two (2) existing package rooftop units, one (1) existing kitchen exhaust hood, and the installation of two (2) new water source heat pump units. The project will also include the installation of destratification fans (Drill Hall only), piping, ductwork, and related controls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment, Piping, & Ductwork 35,000
2 Outdoor Air Handler, Maintenance Shop (5,500 cfm) 65,000
3 Outdoor Air Handler, 150th Maintenance (4,000 cfm) 49,000
4 Outdoor Air Handler, Drill Hall (6,000 cfm) 71,000
5 Outdoor Air Handler, Locker/Restroom (4,000 cfm) 49,000
6 Kitchen Make-Up Air Unit (7,500 cfm) 40,000
7 Kitchen Exhaust Hood with Fire Suppression 75,000
8 Water Source Heat Pump (5 tons) 13,000
9 Water Source Heat Pump (1 tons) 3,000
10 Rooftop Unit (10 tons, ERV) (2 ea @ $26,500/ea) 53,000
11 Air Distribution & Ductwork Modifications 40,000
12 Condenser Water Piping & Accessories 25,500
13 Temperature Control System Modifications 140,000
14 Testing, Balancing, & Commissioning 20,000
15 Crane/Rigging 15,000
16 Electrical Modifications 25,000
Total 693,500