View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7599
Project Title: Roof Replacement, USPFO Building
Agency: SPWD
Division: SPWD
Department: Admin
Project Manager: AJL
Description: Replace Single-Ply Roof Membrane
Location: Carson City
DI_Location_2: 0
Project Description: This project would provide for a single ply roofing system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Membrane Tear Off & Disposal (30,000 sf @ $1/sf) 30,000
2 Membrane Installation (30,000 sf @ $10.5/sf) 315,000
3 Misc Components (30,000 sf @ $1/sf) 30,000
4.
5.
6.
7.
8.
9.
10
11.
12.
13.
14.
15.
16.
Total 375,000