Application ID: 7598
Project Title: Install Emergency Generator (Washoe County Armory)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: CAD
Description: Install emergency generator at Washoe County Armory to carry out critical missions.
Location: Stead
DI_Location_2: 0
Project Description: The scope of this project will install an emergency generator and automatic transfer switch at the Washoe County Armory located near Stead. Currently, there is no back up power at this facility.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace 750 KW Generator 400,000
2 Transfer Switches 50,000
3 Installation (Bollards & Pad) 60,000
4 Conduit, Conductors, Trenching & Repairs (800 lf @ $60/lf) 48,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 558,000