View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7583
Project Title: Replace Building 6 Overhead Doors (Carlin Readiness Center)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: RLC
Description: Replace 9 overhead glass panel doors with insulated coiling doors on Building 6 (old fire station)
Location: Carlin
DI_Location_2: 0
Project Description: This project will design and replace 9 overhead glass panel doors with insulated coiling doors on Building 6 (old fire station). The project will use insulated aluminum extruded slats with a minimum 14 gauge aluminum with powder coated finish. Operation to use motorized openers as recommended by Manufacturer. high wind/hurricane rated,

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition (9 ea @ $2,000/ea) 18,000
2 Insulated Overhead Doors (9 ea @ $19,710/ea) 177,390
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 195,390