View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7579
Project Title: Lighting Upgrade (Las Vegas Readiness Center Site)
Agency: NArmyNG
Division: NArmyNG
Department: Military
Project Manager: CAD
Description: Replace exterior bollard lights, wall lighting, pole lighting and flag pole lighting fixtures and the storage building fixtures.
Location: Las Vegas
DI_Location_2: 0
Project Description: The scope of this project is to upgrade the lighting to LED fixtures. Replacing the exterior lighting includes bollard lights, lighting controls, wall lighting, pole lighting and flag pole lighting at the Las Vegas Readiness Center Site. Room B232 of the main building, storage building and site are all included.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Pole Mounted Fixtures (39 ea @ $2,500/ea) 97,500
2 Wall Mounted Fixtures (37 ea @ $1,500/ea) 55,500
3 Bollards (20 ea @ $1,500/ea) 30,000
4 Surface Mount 1'X4' LED Fixtures (54 ea @ $800/ea) 43,200
5 Lighting Controls 15,000
6 Flag Pole Lighting (3 ea @ $1,000/ea) 3,000
7
8
9
10
11
12
13
14
15
16
Total 244,200