View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7577
Project Title: Wells Conservation Camp NDF Office ADA Restroom
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: MCR
Description: Remodel unisex restroom and add shower for ADA compliance
Location: Wells
DI_Location_2: 0
Project Description: This Project will remodel the existing restroom and shower to the Wells Conservation Camp's NDF Office to comply with the American with Disabilities Act Guidelines. The work will also include interior door and hardware modifications, exterior entry / land

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Unisex Restroom / Shower Remodel 30,000
2 Door Hardware (7 ea @ $500/ea) 3,500
3 Mechanical / Electrical Modifications 8,000
4 ADA Signage (3 ea @ $350/ea) 1,050
5 Door / Frame / Threshold (2 ea @ $2,500/ea) 5,000
6 Concrete Landing / Entry Modification (400 lf @ $12/lf) 4,800
7.
8.
9.
10.
11.
12
13
14
15
16
Total 52,350