View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7576
Project Title: Install Security Camera System (Minden Interagency Dispatch Center)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: CAD
Description: Install cameras, single viewing station and digital storage . This is for the Sierra Front Interagency Dispatch Center and Hangar.
Location: Minden
DI_Location_2: 0
Project Description: The scope of this project is to install a security system which will include video monitoring of the buildings' access points and add secure entry and exit key pads. This facility currently does not have security equipment to protect personnel, equipment, or emergency management operations.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Door Controls with Locks (5 ea @ $4,000/ea) 20,000
2 Door Controls - Head End Equipment 8,000
3 Cameras Inside (2 ea @ $4,000/ea) 8,000
4 Cameras Outside (7 ea @ $5,000/ea) 35,000
5 Camera - Head End Equipment 20,000
6 Trenching, Conduit, Conductor Install (100 lf @ $50/lf) 5,000
7 Badging Equipment 20,000
8 Replace Combiner Box 8,000
9
10
11
12
13
14
15
16
Total 124,000