Application ID: 7572
Project Title: Security Upgrades (Ely Industrial Shop)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: CSB
Description: Provide Shop, Office and Yard security upgrades with security alarms and barbed wire addition at Ely Industrial Shop Facility
Location: Ely
DI_Location_2: 0
Project Description: The scope of this project is to add the needed security upgrades including security alarms in existing office and the Industrial shop and the addition of three strand barbed wire to the top of the existing perimeter chain link fencing.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Selective Demolition 25,000
2 Security Alarms at Shop & Office 10,000
3 Barbed Wire (10,000 lf @ $2.5/lf) 25,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 60,000