Application ID: 7569
Project Title: Welding Shop Electrical and Energy Upgrades (Western Regional Headquarters)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: RLC
Description: Electrical upgrades and energy retrofit of the welding shop's exterior envelope.
Location: Other
DI_Location_2: 0
Project Description: This project will upgrade the welding shop's electrical power to accommodate additional welding stations and add insulation to the building's exterior envelope. The electrical upgrades include a new 400 amp electrical service panel which will allow for up to four welding stations and increased lighting levels with energy efficient light fixtures. Insulation of the exterior envelope includes the installation of wall framing and insulation at the perimeter walls with protective paneling on the interior, installation of new insulated overhead doors, replacement of single pane windows with insulated window units, and insulating the underneath side of the metal roofing.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Walls / Insulation / Paneling / Paint (1,824 sf @ $12/sf) 21,888
2 Insulated Sectional Overhead Doors (3 ea @ $4,500/ea) 13,500
3 Insulated Window Units (4 ea @ $650/ea) 2,600
4 Ceiling Insulation (1,248 sf @ $3.5/sf) 4,368
5 400 Amp Service 45,000
6 Power Distribution 8,500
7 Lighting (1,248 sf @ $5/sf) 6,240
8 Air Compressor 6,000
9
10
11
12
13
14
15
16
Total 108,096