View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7565
Project Title: Install Backflow Prevention Assemblies and Replace Well Equipment (WRH)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: BJW
Description: Install backflow prevention assemblies at the Western Region Nursery and replace well equipment at the Western Region Headquarters at Washoe Lake.
Location: Other
DI_Location_2: 0
Project Description: This project will design and install backflow prevention facilities at the Western Region Nursery and replace well equipment in the Western Region Headquarters. The project scope includes installation of underground backflow preventers and associated electrical connection, removal of existing well equipment and appurtenances, installation of well equipment and appurtenances, and construction of an interior partition wall.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Nursery Backflow Preventers (2 ea @ $17,500/ea) 35,000
2 Electrical Service to Backflow Preventers (200 lf @ $50/lf) 10,000
3 Well Pump 10,000
4 Well Pressure Tank 7,500
5 Well Electrical Upgrades 2,500
6 Replace Well Piping & Valves (75 lf @ $80/lf) 6,000
7 Remove Existing Well Equipment 4,000
8 Interior Wall in Headquarters (500 sf @ $30/sf) 15,000
9
10
11
12
13
14
15
16
Total 90,000