Application ID: 7560
Project Title: Hazardous Storage Facility (Ely Conservations Camp)
Agency: SPWD
Division: SPWD
Department: Admin
Project Manager: KRS
Description: Construction of a small hazardous storage area
Location: Ely
DI_Location_2: 0
Project Description: The scope of this project is to construct a small hazardous waste storage area at the facility.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Concrete Footing & Slab (400 sf @ $50/sf) 20,000
2 Shade Structure 16,000
3 Flammable Safety Cabinet (2 ea @ $1,700/ea) 3,400
4 Two Drum Spill Containment (2 ea @ $450/ea) 900
5 Metal Storage Rack (3 ea @ $350/ea) 1,050
6 Lighting 2,500
7
8
9
10
11
12
13
14
15
16
Total 43,850