View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7555
Project Title: Ely Conservation Camp NDF Office ADA Restroom
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: MCR
Description: Remodel unisex restroom for ADA compliance
Location: Ely
DI_Location_2: 0
Project Description: This Project will remodel the restroom at the Ely Conservation Camp NDF Office to comply with the American with Disabilities Act Guidelines. The work will also include door and hardware modifications

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remodel Unisex Restroom 25,000
2 Door Hardware (7 ea @ $500/ea) 3,500
3 Mechanical / Electrical Modifications 5,000
4 ADA Signage (3 ea @ $350/ea) 1,050
5 Concrete Landing / Entrance (240 sf @ $12/sf) 2,880
6.
7.
8.
9.
10.
11.
12
13
14
15
16
Total 37,430