Application ID: 7554
Project Title: Carlin Conservation Camp NDF Office ADA Restroom
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: MCR
Description: Add new unisex restroom with shower for ADA compliance and add shower to existing unisex restroom
Location: Carlin
DI_Location_2: 0
Project Description: This Project will construct a new ADA Unisex Restroom and Shower to the Carlin Conservation Camp's NDF Office to comply with the American with Disabilities Act Guidelines. The work will also include door and hardware modifications, exterior entry / landin

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Unisex Restroom / Shower 30,000
2 Door Hardware (7 ea @ $500/ea) 3,500
3 Mechanical / Electrical Modifications 8,000
4 ADA Signage (4 ea @ $350/ea) 1,400
5 Door / Frame 1,500
6 Remodel Existing Restroom 5,000
7 Concrete Landing / Entry Modification (240 lf @ $12/lf) 2,880
8.
9.
10.
11.
12
13
14
15
16
Total 52,280