Description: Add new unisex restroom with shower for ADA compliance and add shower to existing unisex restroom
Location: Winnemucca
DI_Location_2: 0
Project Description: This Project will construct a new ADA Unisex Restroom and Shower to the Humboldt Conservation Camp's NDF Office to comply with the American with Disabilities Act Guidelines. The work will also include door and hardware modifications and adding a shower to

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Unisex Restroom / Shower 30,000
2 Door Hardware (2 ea @ $500/ea) 1,000
3 Mechanical / Electrical Modifications 8,000
4 ADA Signage (5 ea @ $350/ea) 1,750
5 Door / Frame 1,500
6 Remodel Existing Restroom 6,000
7.
8.
9.
10.
11.
12
13
14
15
16
Total 48,250