SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7552
Project Title: Stewart Conservation Camp NDF Office ADA Restroom
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: MCR
Description: Remodel unisex restroom and shower for ADA compliance
Location: Carson City
DI_Location_2: 0
Project Description: This Project will remodel the existing restroom and shower to the Stewart Conservation Camp's NDF Office to comply with the American with Disabilities Act Guidelines. The work will also include exterior entry / landing modifications.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Unisex Restroom / Shower Remodel 5,000
2 ADA Signage (2 ea @ $350/ea) 700
3 Concrete Landing / Entry Modification (200 sf @ $12/sf) 2,400
4.
5.
6.
7.
8.
9.
10.
11.
12
13
14
15
16
Total 8,100