View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7549
Project Title: Pavement Maintenance (Elko Interagency Dispatch Center)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: MJM
Description: Patching, Sealing and Striping of existing AC Pavments
Location: Elko
DI_Location_2: 0
Project Description: This project will perform miscellaneous patching on the parking lot and helipad tarmac, crack seal, seal coating and re-striping at the Elko Interagency Dispatch Center.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Crack Seal (70,000 sf @ $.1/sf) 7,000
2 Seal Coat (70,000 sf @ $.3/sf) 21,000
3 Patching, Front Lot (800 sf @ $10/sf) 8,000
4 Patching, Tarmac (1,200 sf @ $12/sf) 14,400
5 Parking Striping 3,500
6 Tarmac Striping 3,000
7
8
9
10
11
12
13
14
15
16
Total 56,900