Application ID: 7546
Project Title: Tarmac Pavement Rehabilitation (Sierra Front Dispatch)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: MJM
Description: Rehabilitate the existing pavement on the tarmac.
Location: Minden
DI_Location_2: 0
Project Description: This project will rehabilitate the AC surface on the tarmac.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Pulverize & Repave Tarmac (40,000 sf @ $3/sf) 120,000
2 Plane Tie Downs (9 ea @ $500/ea) 4,500
3 Striping 1,000
4 Crack Seal (90,000 ea @ $.1/ea) 9,000
5 Seal Coat (130,000 ea @ $.3/ea) 39,000
6.
7
8
9
10
11
12
13
14
15
16
Total 173,500