Application ID: 7542
Project Title: Rain Gutters and Ice Dam Protection, Elko Headquarters Shop Building
Agency: CNR
Division: CNR
Department: CNR
Project Manager: AJL
Description: Install new rain gutters and ice dam protection.
Location: Elko
DI_Location_2: 0
Project Description: This project would provide new rain gutter and ice dam protection.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Rain Gutters & Down Spouts (300 lf @ $25/lf) 7,500
2 Ice Dam Protection (100 lf @ $15/lf) 1,500
3 Misc Components (300 lf @ $8/lf) 2,400
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14
15
16
Total 11,400