View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7535
Project Title: Parking Lot Maintenance (NDF Northern HQ)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: MJM
Description: Crack and slurry seal, make repairs and re-stripe pavement.
Location: Elko
DI_Location_2: 0
Project Description: This project will replace the existing drainage swale with a PCC valley gutter, perform miscellaneous cutting and patching, crack seal and slurry seal the asphalt pavement, and replace the existing ADA accessible walkway into the office.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Crack Seal (36,000 sf @ $.25/sf) 9,000
2 Seal Coat (36,000 sf @ $.25/sf) 9,000
3 Cut in PCC Valley Gutter (200 lf @ $60/lf) 12,000
4 Patching (1,000 sf @ $10/sf) 10,000
5 Parking Striping 600
6 ADA Striping 120
7 Signage 450
8 ADA Walkway (1,000 sf @ $10/sf) 10,000
9
10
11
12
13
14
15
16
Total 51,170