SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7529
Project Title: Ely Industrial Shop
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: CSB
Description: Design and construction of a 5,000 sf industrial shop.
Location: Ely
DI_Location_2: 0
Project Description: The scope of this project includes the design and construction of a 5,000 sf metal shop building with 600 sf of office space, 400 sf for a compressor room, 1,000 sf of mezzanine storage, and 4,000 sf of shop area with 4 roll-up bay doors and one vehicle lift. This facility would provide a weather protected and safe working space needed for general vehicle maintenance, fire crew/utility truck fabrication and assembly, parts storage, and offices.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Site Earthwork & Utilities 125,000
2 Concrete Site Work (3,000 ea @ $15/ea) 45,000
3 Maintenance Shop Building (5,000 sf @ $225/sf) 1,125,000
4 Fencing (300 lf @ $25/lf) 7,500
5 Vehicle Lifts 25,000
6
7
8
9
10
11
12
13
14
15
16
Total 1,327,500