Application ID: 7528
Project Title: Vehicle and Equipment Parking Area (Ely NDF Industrial Shop Building)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: MJM
Description: Design and construct a new vehicle equipment parking area in front of the shop and administration buildings.
Location: Ely
DI_Location_2: 0
Project Description: This project will design and construct a new parking and work area in front of the administration and shop buildings.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 ADA Parking (500 sf @ $12/sf) 6,000
2 ADA Striping & Signage (4 ea @ $500/ea) 2,000
3 AC Pavement (40,000 sf @ $6/sf) 240,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 248,000