View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7527
Project Title: Advance Planning - Heavy Equipment Shop and Renovation (NDF Northern Region II)
Agency: Forestry
Division: Forestry
Department: CNR
Project Manager: RMO
Description: Design through construction documents for a 7,200 sf equipment repair and fabrication shop and convert the existing 4,600 sf shop into a storage facility.
Location: Elko
DI_Location_2: 0
Project Description: The scope of this project is to complete the design through construction documents for a new heavy equipment repair and fabrication shop consisting of 6,000 sf including space for offices, restrooms, showers and support facilities under a 1,200 sf storage mezzanine. The new building would be located north of the existing shop at the Nevada Division of Forestry compound situated on Nevada Youth Training Center property. In addition, construction documents will be completed for the remodel of an existing 4,600 sf shop building to include safety upgrades, and convert the building into a storage facility for equipment that is currently stored outdoors and covered with tarps for weather protection.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Metal Building Repair Shop (6,000 sf @ $310/sf) 1,860,000
2 Over Excavation & Backfill (1,450 cy @ $30/cy) 43,500
3 Concrete Apron (3,800 sf @ $24/sf) 91,200
4 Exhaust Extraction System 112,000
5 Hydraulic Lifts 106,000
6 Overhead Bridge Crane 148,000
7 Mezzanine (1,200 sf @ $100/sf) 120,000
8 Waste Oil Furnace with Storage Tanks 65,000
9 Fire Water Supply (500 lf @ $100/lf) 50,000
10 Off-Site Electrical (1,200 lf @ $106/lf) 127,200
11 Sewer Line (1,100 lf @ $88/lf) 96,800
12 Gas Line Extension (1,200 lf @ $65/lf) 78,000
13 Lighting & Electrical Upgrades (4,600 sf @ $18/sf) 82,800
14 Renovate Restrooms (2 ea @ $18,000/ea) 36,000
15 Renovate HVAC System (4,600 sf @ $14/sf) 64,400
16 Install Fire Protection System (4,600 sf @ $12/sf) 55,200
Total 3,080,900